Relining of Multiple Stormwater Pipe Sections

NUFLOW NORTHWEST SYDNEY
Industrial Manufacturing Facility | MELROSE PARK NSW

PROJECT OVERVIEW

Nuflow was engaged to rehabilitate several damaged sections of underground stormwater pipe at the rear of the facility. The aging 150mm and 100mm pipes had developed fractures and structural deterioration, posing risks to both site safety and drainage efficiency. With traditional excavation ruled out due to restricted access, tight timeframes, and the need to minimise operational disruption, trenchless relining was chosen as the most effective solution. The project scope included relining two 4-metre sections and one 5-metre section of 150mm pipe, along with an additional 3.5-metre section of 100mm pipe identified during the works. To enable a seamless installation, custom bladders were manufactured and tested ahead of schedule, allowing crews to begin work immediately upon arrival on-site.

THE CHALLENGE

  • Multiple fractured and deteriorated stormwater pipes (150mm & 100mm) at the rear of the facility
  • Structural deterioration threatening drainage efficiency and site safety
  • Restricted access behind the building made traditional excavation unfeasible
  • Tight timeframe requiring efficient, non- invasive rehabilitation
  • Need to minimise disruption to Speedibake’s daily operations

THE SOLUTION

NuFlow deployed a specialised team to carry out the pipe relining works over multiple days. The project followed a systematic approach:

THE RESULTS

The relining works successfully restored the structural integrity of all targeted stormwater pipes, eliminating the need for excavation and replacement. The 4-metre and 5-metre liners were installed as specified, with CCTV verification confirming their effectiveness. The additional 3.5-metre reline on the 100mm blue line pipe also set well, ensuring proper flow and preventing further deterioration. All works were carried out within the scheduled timeframe, and safety standards were strictly maintained, with temporary barriers and fencing securing the site throughout the project. Upon completion, all fencing, bollards, and equipment were packed down and removed, leaving the facility with renewed and structurally sound stormwater assets.

NUFLOW’S AGING INFRASTRUCTURE MAINTENANCE AND REHABILITATION

For information on how Nuflow can help maintain and rehabilitate your potable water assets— including pressure main relining, concrete pipeline repairs, and trenchless rehabilitation of critical supply infrastructure—contact our team of specialists. We deliver safe, compliant solutions for even the most complex potable water pipe repair projects.

Latest news

Nuflow was engaged to carry out a CCTV investigation of a 375 mm stormwater line connected to a grated side entry pit on the Sunnyholt Road on-ramp of the M7 Motorway. Given the high-risk location on a major freeway, safety and traffic management were top priorities while advanced camera and tractor CCTV technology captured critical internal condition footage to inform future rehabilitation planning.

Nuflow was engaged to rehabilitate a combined sewer and stormwater pipe system in Blacktown that had failed due to root intrusion, cracks and joint deterioration. Using trenchless Blueline relining and inspection technologies, NuFlow restored structural integrity and reliable flow without excavation, reducing disruption to council operations and the community.

Nuflow was engaged to rehabilitate a 300 mm reinforced concrete stormwater pipe at Vincent and Paul Court in Baulkham Hills. Using the advanced IMPREG UV structural liner system, NuFlow restored the pipe’s strength and service life without disruptive excavation, overcoming access challenges and debris obstructions to deliver a durable trenchless solution that minimised surface disruption.