{"id":6114,"date":"2019-07-04T17:27:00","date_gmt":"2019-07-04T07:27:00","guid":{"rendered":"https:\/\/nuflow.net\/case-study-sensitive-government-site-darwin\/"},"modified":"2023-08-10T11:50:27","modified_gmt":"2023-08-10T01:50:27","slug":"case-study-sensitive-government-site-darwin","status":"publish","type":"post","link":"https:\/\/nuflow.net\/case-study-sensitive-government-site-darwin\/","title":{"rendered":"Stormwater Pipes Darwin – Sensitive Government Site (Case Study)"},"content":{"rendered":"

With temperatures nearing 40 degrees and threatening wet-season rains to contend with, relining 225mm underground stormwater pipes proved both challenging and rewarding for Nuflow Darwin’s Mick Hodgetts.<\/p>\n

Cracks in newly-installed 225mm reinforced concrete stormwater pipes.New paving and landscaping had been completed above and excavation was not a viable option.<\/p>\n

THE NUFLOW SOLUTION<\/h2>\n

With the help of an air-conditioned van and plenty of ice, Nuflow’s Blueline relining system was installed over three cracked lengths of pipe:<\/p>\n